Proof-of-Concept Build

Construction Phase - Week 2



31 July to 06 August 2022 


Having placed all 4 platform sections on the scaffold it is now time to begin hanging the longitudinal trusses.

DH1-1

First the port side inner truss was hung...

DH1-2

Then the starboard side inner truss was hung followed by the starboard side outer truss.

DH1-3

After the port outer truss, the 4th and final truss was in place, the next step was to begin hanging the big black floats,

DH1-3

Starting from the rear and working forward on each side.

DH1-3

After the last of 6 floats was hung we were ready to conduct the first launch test.

DH1-3