Proof-of-Concept Build
Construction Phase - Week 2
07-13 August 2022
Having passed the first float test, the houseboat platform was placed back in the hangar.
Then external bulkheads were once again attached to the platform, this time on top of the launch and recovery trailer.
Internal bulkheads were attached as well. This is a view of the bathroom bulkhead from the living room.
Next it was time to see if the bathtub was going to fit. GREAT! It fits like a glove!
Even better... The door swings!
The forward bulkhead with the patio door was also attached.
At this point bulkheads are in varied states of completion.
The ones with few or no electrical or plumbing connections are further along than those with more.
Finishing all remaining electrical or plumbing connections is the next order of business.
Hey! Look who's adding another coat of paint to the truss skirt. Doing a GREAT job sweetie!