Proof-of-Concept Build

Construction Phase - Week 7



19-25 June 2022 


All components subject to water/weather exposure need to be protected. A coat of paint was added to each of the scaffold sections early in week 7.

DH1-1

Once dry, the trusses were setup in the eventual houseboat configuration on the hangar floor.

DH1-2

Platform sections are then layed on top and attached starting with section # 3.

DH1-3

All platform sections are now attached to the truss frame. I hope you all have seen the great pictures Anita sent from her visit yesterday.

DH1-4

With all platform sections attached, it was time to start installing bulkheads.

DH1-5

In this picture you can see the 2 large window openings at the rear. Both are in the bedroom. The window opening forward is in the galley followed by another large window opening in the living room.
I love it when an idea begins to take shape!

DH1-6

Here you can see into the houseboat through the large opening which will hold the sliding patio door. Under the patio is outside stowage.

DH1-6

Friday it took about 7 hours to disassemble. That effort represented about 60% of a finished houseboat disassemble task.
That task was specified as 'needing to be completed in less than 48 hours' at any marina.   Woo-hoo! - Things are coming together better than hoped!