Proof-of-Concept Build

Construction Phase - Week 8



26 June - 02 July 2022 


Having successfully finished the first 'assembly' and 'dis-assembly' last week, it was now time to focus on service infrastructure installation - electrical, plumbing and EPS insulation.
Here you see external bulkhead section # 7 and the window opening is for one of the 3 bedroom windows.

DH1-1

Anyone know what this is?
It is called a hot knife and it is the best tool I've found for cutting EPS and XPS rigid insulation.
What about the little black ball?   Anyone?

DH1-2

That ball (after being heated and placed on top of the EPS) made this cavity with just gravity. Pretty cool eh?
I'm using a heated 3/4" ball bearing to make round columns in the EPS insulation for plumbing the 1/2" pex pipe (fits perfect by-the-way) and to run electrical cables.

DH1-3

This is the starboard forward external bulkhead section # 3 with EPS insulation installed. The large window opening is in the living room while the smaller window opening is in the galley.

DH1-3