Proof-of-Concept Build

Construction Phase - Week 2



03-09 July 2022 


Production slowed this week as family was visiting from out west. Great to see everyone!
The vinyl windows and doors for the houseboat arrived this week.

DH1-1

I started adding interior veneer to bulkheads this week. See the little roundish cuts at the bottom of some EPS sheets?
That is where the connections are made that hold the bulkhead to the deck. When assembly is nearly complete that area is covered with baseboard trim.
The portable lift is about to move eB3 and lean it on other bulkheads awaiting the second assembly.
Ya, I know, there is overspray on the branding which I'll fix later (I'm hoping to sell my e-houseboat plan once I've finished sea trials).

DH1-2

Oh, I also installed the sliding patio door in external bulkhead section # 1 this week.

DH1-3